Corby's dwellings

Oct - 17

You will find below the final system design explanation.

May - 18

As expected, the work started: the first plot foundations were marked for concrete and Earth Energy Bank (EBB) paving the way for the future ecohomes.

Jan - 19

At the end of December 2018, the drainage and the rear acess road of the block properties have been built, the installation of boreholes for the Earth Energy Bank (EBB) and the foundations for the first 4 homes.

In January 2019, the block and beam flooring are going to be installed in order to erect the panelized wall system. Also, will be made the foundations for the next set of new homes.

Jan - 19

At the end of December 2018, the drainage and the rear acess road of the block properties have been built, the installation of boreholes for the Earth Energy Bank (EBB) and the foundations for the first 4 homes.

In January 2019, the block and beam flooring are going to be installed in order to erect the panelized wall system. Also, will be made the foundations for the next set of new homes.

Here are 2 videos of the visit of Corby's pilot on May 30th, 2019

May - 19

Sep - 19

The Earth Energy Bank has finally been completed for the first 10 homes, the photovoltaic panels have been fully installed on the first set of homes as well, and the heat pump installation is completed. Data has been collecting since then with the aim to quantify the benefits and savings.

Here you have the links for 3D visual animation of the Corby eco-homes. You can walk around the building and see the Earth Bank installed!